City staff unveiled staggering estimates for grade separations, ranging from $420M to $1.3B, with construction timelines stretching to 2032—could this reshape our city's future?

Click to read more!

#PaloAltoSantaClaraCounty #CA #CitizenPortal #PaloAltoProjects #InfrastructureDevelopment
Committee hears $420M–$1.3B estimates and multi‑year construction schedules for grade separations
Staff presented conceptual, year‑of‑expenditure cost ranges and schedules based on 15% design: Churchill ~ $420–$450M (3–4 years); Charleston alone ~$480–$530M (4 years); Meadow+Charleston concurrent ~$1.0–$1.1B (5 years) or sequential ~$1.2–$1.3B (9 years); escalation assumed to a 2032 construction midpoint.