#RobesonTownship
Robeson Township's Old River Road Bridge project is facing a long wait as federal funding won't kick in until 2030, but engineers are pushing for a less invasive twin-cell precast box culvert solution!

Get the details!

#RobesonBerksCounty #PA #CitizenPortal #FederalFunding #RobesonTownship
Old River Road Bridge work federalized, construction not expected until 2030; engineers favor twin-cell precast box culvert
Township manager briefed supervisors that PennDOT and FHWA expect construction funding to be available in 2030 and that engineers recommended a twin-cell precast box culvert over bridge rehabilitation because of abutment decay and risks to a nearby historic property, with Robeson Township responsible for future maintenance.
citizenportal.ai
August 17, 2026 at 6:20 AM