#SaskPower
Excellent piece outlining lack of planning & public transparency, & high-cost risks SaskPower is taking with its coal-&-nuclear-power strategy.
In August Saskatchewan’s Rate Review Panel declined to approve a 2027 rate increase & “called for more clarity & transparency from SaskPower”. 1/
Opinion: Open, transparent planning needed for SaskPower
SaskPower is operating under considerable regulatory and legal risk.
thestarphoenix.com
September 19, 2026 at 10:06 PM
"…we have seen the capital costs [to refurbish SaskPower's coal-fired power stations] balloon from $900M… to $11.4B…

Most external authorities now put the cost of Sask's coal refurbishment plan at about $30B. Every other option for Saskatchewan’s power future is less expensive…" #Sask #SkPoli
Opinion: Open, transparent planning needed for SaskPower
SaskPower is operating under considerable regulatory and legal risk.
thestarphoenix.com
September 19, 2026 at 7:15 PM
Absolutely nobody who lives in Saskatchewan is surprised. There never was a plan.
leaderpost.com/news/saskpow...
SaskPower lacks clear plan to address missed net-zero targets: Auditor
The provincial auditor has issued two recommendations to SaskPower with regard to its plans to reduce greenhouse gas emissions.
leaderpost.com
December 5, 2024 at 1:28 AM
Disappointed that SaskPower is appealing this penalty.

Right now SaskPower should continue to invest in OHS & improve its safety culture. Nothing is more important.

Paying lawyers & using court time to try to lower this penalty sends the wrong message. #ohs #canlab

www.cbc.ca/news/canada/...
SaskPower appealing court order to pay $840K fine for deaths of 2 workers | CBC News
SaskPower says it is appealing an $840,000 fine that a Weyburn court ordered it to pay following the death of two workers in 2020.
www.cbc.ca
November 17, 2024 at 1:58 PM
Saskatchewan’s SaskPower should be doing this.
August 7, 2026 at 10:44 PM
Finally, something positive happens in Saskatchewan... www.cjme.com/2024/11/15/n...
New Saskatchewan wind power facility now online
CEO Rupen Pandya says SaskPower is on track to achieve a net-zero power system by 2035.
www.cjme.com
November 16, 2024 at 4:02 PM
Minister Jeremy Harrison has just directed SaskPower to rebuild its coal-fired power plants and continue running them past 2030. The letter directs SaskPower to begin by putting Boundary Dam unit 4 back in service. This decision is problematic for many, many reasons and I list some of them below:
June 18, 2025 at 9:15 PM
Then you need to build renewable energy up faster than the SaskParty is allowing SaskPower to do so.
#skpoli #cdnpoli
June 3, 2025 at 7:13 AM
"Crews have been dispatched and are determining the cause and repair time for the outage reported in Love."

#SundaySentence by @sask-power.bsky.social from earlier this week: x.com/SaskPower/st...

... and fortunately: x.com/SaskPower/st...

(h/t @brendaschmidtpoet.bsky.social)
January 12, 2025 at 6:44 PM
Must-read column by engineer Bob Halliday. Open, transparent planning needed from SaskPower. Most external authorities now put the cost of SaskPower’s coal refurbishment plan at about $30 billion. Every other option for Saskatchewan’s power future is less expensive than the present course. #skpoli
"…we have seen the capital costs [to refurbish SaskPower's coal-fired power stations] balloon from $900M… to $11.4B…

Most external authorities now put the cost of Sask's coal refurbishment plan at about $30B. Every other option for Saskatchewan’s power future is less expensive…" #Sask #SkPoli
Opinion: Open, transparent planning needed for SaskPower
SaskPower is operating under considerable regulatory and legal risk.
thestarphoenix.com
September 20, 2026 at 4:09 AM
The AI Data Centre-Driven Privatization of SaskPower Is Underway. You Knew It Was Coming.
Inside the quietest privatization in Saskatchewan history — no legislature, no regulator, no disclosure.
by Tammy Robert
The AI Data Centre-Driven Privatization of SaskPower Is Underway. You Knew It Was Coming.
Inside the quietest privatization in Saskatchewan history — no legislature, no regulator, no disclosure.
tammyrobert.substack.com
September 21, 2026 at 10:38 AM
Leaked SaskPower documents show 'extreme' risk in $26B coal refurbishment plan
www.cbc.ca/news/canada/...
Leaked SaskPower documents show 'extreme' risk in $26B coal refurbishment plan | CBC News
Documents predict the provincial government's coal refurbishment plan would increase the average cost of electricity by 95 per cent by 2040.
www.cbc.ca
May 14, 2026 at 12:28 AM
Jeremy Harrison, the minister responsible for SaskPower and the Crown Investments Corporation, gave a glowing endorsement of keeping coal going and to eventually transition to SMR nuclear as a replacement. Basically pursuing the worst of all options
www.sasktoday.ca/southeast/es...
SaskPower minister explains reasoning for keeping coal in the mix
SaskPower is exploring options its conventional coal-fired power units.
www.sasktoday.ca
June 20, 2025 at 11:07 PM
They are serious about pollution reduction in Europe, while your silly AI for Everyone idea is causing corrupt build-outs in Saskatchewan and elsewhere.
New 900MW gas power plants to power these things are not allowed if SaskPower does it, so why can effing Bell do it?!
#AIDataCentre #cdnpoli
September 16, 2026 at 3:02 PM
lmao it’s Bugsday the Hour of Rage at SaskPower
September 19, 2026 at 8:46 PM
@kissedafrog.bsky.social

This hydroelectric power station, owned and operated by SaskPower, generates electricity from the waters of the Churchill River, providing energy to Saskatchewan's homes and businesses.
Sandy Bay, Saskatchewan, Canada

#StressBreak

Rob 😊
March 31, 2025 at 2:40 AM
Sask legit could use more power. (I used to work at SaskPower.) We could have been investing in wind and solar for decades but instead we’ve done fuck all but yearn for nuclear.
The plant is forecast to start up in 2030 at capital cost of ~$7B for 300MW. Similar-sized wind & gas plants (300MW) in Saskatchewan are currently forecast at $750-850M (~1/8 the capital cost).
However, “‘No nuclear plant of any type has ever come in on budget, let alone a new untested design’”.
May 8, 2025 at 11:58 PM
SASK. PARTY MLAS CHAN, CRASSWELLER BLOCK INVESTIGATION INTO SHADY SASKPOWER OVERSPEND
December 11, 2025 at 5:55 PM
Maybe I’m too anachronistic here but crown corporations should be beholden to only hire people who live in the area in which taxes are paid to the crown. Eg. No hiring call centre dinguses from Nanahoogistan because it’s cheaper than hiring SK folks for SGI/SaskTel/SaskPower/SaskEnergy employees.
July 25, 2025 at 9:51 PM
The majority of trolls responding to Conway's Facebook post about SaskPower ripping Canada off with new COAL to the tune of $26 billion (yes, with a B), are just the stupidest people in the province.
#skpoli www.facebook.com/mearaconwayM...
Entire SK budget was only $21 billion!
www.facebook.com
May 7, 2026 at 11:49 PM
SaskPower sucks.
SGI sucks.
Yes, I'm ranting.
Yes, it's justified.
SaskPower charged me $500 last month when normally it's $80.
This month they want $400 when it should be $80. I called to get their bad estimates fixed, and they said it's up to me to fix them instead!?
April 9, 2025 at 10:14 PM
Unnecessary (part 1) – SaskPower identified options for its electricity future in its extensive supply planning public engagement. Extending the life of coal plants was not on the table. Viable alternatives exist to power the province, including ‘dispatchable’ natural gas power plants.
June 18, 2025 at 9:15 PM
You're letting Bell pollute the air from Saskatchewan almost as much as SaskPower plans to!
#cdnpoli #skpoli #AIDataCentre
September 15, 2026 at 9:48 PM
The government of Saskatchewan advertising our province as "sustainable" while expanding coal mining is the most hypocritical thing ever.

www.theglobeandmail.com/business/art...
Saskatchewan looks to run conventional coal for power well beyond Ottawa’s 2030 phaseout deadline
Minister responsible for SaskPower says preliminary numbers show refurbishing coal power plants cost billions of dollars less than building new power sources and would avoid installing more transmissi...
www.theglobeandmail.com
February 17, 2025 at 10:06 PM