#PurpleLineMD test train rolling through the UMD campus
No edits—just progress in motion 🚆 We’re closer than you think!
March 26, 2026 at 12:37 AM
The Purple Line is testing light rail vehicles! A major milestone as we transform communities. See testing video on our YouTube page: youtu.be/lx8Eg9HXelQ #PurpleLinePoweredUp #PurpleLineProgress #PurpleLinetransformation #PurplelineMD #ConnectingCommunities
April 3, 2025 at 4:20 PM
#PurpleLineprogress is moving! 🚆 50% of tracks are installed on this 16-mile project from Bethesda to New Carrollton. Learn more: purplelinemd.com/progress/. #ConnectingCommunities #MDOTCares #PurpleLineMD #MTAPurpleLine
June 3, 2025 at 4:39 PM
Forgive my foaming, but y'all, you can see the #PurpleLineMD trains outside the Glenridge railyard.
November 21, 2025 at 10:36 PM
Nearly complete @PurpleLineMD Riverdale Park North UMD on River Rd! This one is grade separated with side platforms. 🟪🚉
September 6, 2025 at 9:24 PM
Look what I saw biking home yesterday! #purplelinemd
May 6, 2026 at 3:40 PM
#PurpleLineProgress can be seen along Ellin Road in New Carrollton where embedded track has been installed. Follow @PurpleLineMD for updates and sign up for alerts: ow.ly/3Np550V7auQ. #ConnectingCommunities #MDOTCares #PurpleLineMD
March 1, 2025 at 2:58 PM
OCS poles are being installed on University Blvd, Piney Branch, and Riverdale Rd! LRV testing is progressing. More info: ow.ly/QlZI50WfPeW. #ConnectingCommunities #MDOTCares #PurpleLineprogress #PurpleLineMD #MTAPurpleLine
July 22, 2025 at 7:33 PM
🟣🚧 NEW🚧🟣
@purplelinemd.bsky.social Road Access Alerts for @montgomerycountymd.bsky.social. The highlighted closures & detours will impact drivers and/or pedestrians during the #PurpleLineMD construction.
🟣Details▶️ tinyurl.com/4yjt8tky #MDRoads #MDTraffic #MDCommuters #Commuting #PurpleLineMD
May 13, 2025 at 8:11 PM
🚆 The #PurpleLineMD is moving forward! New Hampshire Ave at University Blvd has reopened ahead of schedule after key track work. Thanks for your patience! More updates: ow.ly/RBkx50VCHIS #PurpleLineProgress #ConnectingCommunities #MDOTcares
April 17, 2025 at 7:55 PM
This #PurpleLineMD flyover video has some of the best views of Silver Spring I've ever seen. www.youtube.com/watch?v=S8ST...
July 16, 2026 at 10:20 PM
Taking the Red Line this weekend? 🔴 🚇 Trains will single track between Medical Center and Friendship Heights to support Maryland Department of Transportation's Purplelinemd, which will feature 21 new stations from New Carrollton to Bethesda. Learn more: wmata.com/weekend
March 5, 2026 at 1:01 AM
A subtle sign that #purplelinemd is coming soon!
March 24, 2025 at 2:21 PM
North tower of the Silver Spring mezzanine is poured and ready! #purplelinemd
December 2, 2024 at 2:50 AM
Purple Line momentum is building with progress! 🚧 One of the latest milestones is the placement of the Capital Crescent Trail pedestrian bridge.  Want to see the full construction journey? Check out our YouTube page: youtu.be/lSa0Y6G60Dw #ConnectingCommunities #PurpleLineMD
January 22, 2025 at 9:05 PM

New #purplelinemd rails on Campus Dr at University
November 21, 2024 at 3:52 PM
#PurpleLineProgress is on track! Crews poured concrete on Bonifant St and started sidewalk replacement from Silver Spring Library to Georgia Ave. For updates: purplelinemd.com. #ConnectingCommunities #MDOTCares #PurpleLineMD #MTAPurpleLine
May 5, 2025 at 2:15 PM
See #PurpleLineProgress in #MontgomeryCounty! Embedded track prep for concrete is underway at Bonifant St., Wayne Ave. at Manchester & Arliss at Long Branch Station. Over 30% of track is installed! Sign up for #PurpleLineMD alerts: purplelinemd.com/updates/#int... #ConnectingCommunities
March 12, 2025 at 3:44 PM
I've been looking for a total of the shared lane miles on the Purple Line & haven't found any, but my measurements have it at about 3.5 miles (out of 16 total miles), or about 21% of the full route. Can @PurpleLineMD or anyone else verify those numbers?
While ~7 years have passed between these images, construction was not occurring most of the time in between due to Governor Hogan’s mismanagement of the project’s contractors.
This section of the line east of Silver Spring is shared roadway traffic with signal preemption.
August 25, 2025 at 9:03 PM
Thank you for your understanding as we work to build a second mezzanine at Bethesda station to connect to Maryland Department of Transportation's Purplelinemd.

Learn more: www.wmata.com/initiatives/...
July 5, 2026 at 6:20 PM
See the #PurpleLineProgress with Heidi Lippman’s vibrant canopy designs at future Connecticut Avenue Station! #PurpleLineMD. 🎨🚇 More updates on our website: ow.ly/74Um50VkicZ #ConnectingCommunities #MDOTCares #PurpleLineprogress
March 19, 2025 at 3:18 PM
Purple Line momentum is building with the construction of the Capital Crescent Trail pedestrian bridge. #PurpleLineProgress continues to advance in #ConnectingCommunities as large pieces of the bridge are delivered this week! Stay up to date on all things Purple Line by following us. #PurpleLineMD
December 12, 2024 at 10:09 PM
🛠️ Our latest newsletter is out! Get updates, meet the Purple Line team, and discover Kefa Café! #ConnectingCommunities #MDOTCares #PurpleLineProgress #PurpleLineMD
English Version: ow.ly/acGU50WhF7w
Spanish Version: ow.ly/yAKv50WhF7x
June 30, 2025 at 6:09 PM
Progress on the Capital Crescent Trail! Crews placed the new bridge over Rock Creek with an inverted truss design for clear views of the creek. Watch more: ow.ly/jgbj50V7aCQ #ConnectingCommunities #MDOTCares #PurpleLineprogress #PurpleLineMD
March 7, 2025 at 3:33 PM
Maryland Purple Line Senior Project Director Ray Biggs II provides the latest progress update on the Purple Line project for Fall 2025. See the full progress video on our YouTube Page: ow.ly/6Ugo50X9ptG. #ConnectingCommunities #PurpleLineprogress #PurpleLineMD