Commission members are raising crucial questions about water use and grid interconnection in the latest data-center ordinance draft, sparking a debate that could impact local ratepayers.

Get the details!

#SalineCounty #KS #CitizenPortal #GridInterconnection #LocalRatepayerProtection
Commission flags water, grid-interconnection and tariff issues in data-center draft
As it reviewed Text 2601, the commission asked staff to clarify how closed-loop cooling and recycled/nonpotable water requirements would be enforced and whether grid interconnection upgrade costs or tariffs could be shifted to local customers for centers below state thresholds.
citizenportal.ai
September 25, 2026 at 11:44 PM
A heated debate is unfolding over who truly pays for grid interconnection costs as developers clash with city officials on the viability of on-site renewable energy solutions.

Click to read more!

#LouisGratiotCounty #MI #RenewableEnergy #CitizenPortal #SustainabilityDebate #GridInterconnection
Electricity and Ameren obligations surface in debate over renewables and who bears interconnection costs
Board members pressed developers and Ameren‑related counsel on who pays for grid upgrades and whether on‑site renewable generation is feasible; developers said large‑load tariffs and construction agreements require the customer to fund needed extensions, and city staff and the board discussed collateral options.
citizenportal.ai
August 5, 2026 at 12:29 AM
News from E+E Leader ⏳ Major U.S. grid interconnection delays now average nearly 5 years — making old project timelines a thing of the past!

⚡ Over 2,060 GW of generation & storage are waiting for… http://dlvr.it/TTJKwP #GridInterconnection #EnergyStorage #RenewableEnergy #SolarPower #CleanEnergy